地坪漆一般施工方法:
General construction method of floor paint:
一、地坪表面的处理
1、 Surface treatment of floor
1、新竣工的工业地坪必须经过一定的养护后方可施工,约28天。
1. The newly completed industrial floor must be maintained before construction for about 28 days.
2、清除表面的水泥浮浆、旧漆以及粘附的垃圾杂物。
2. Remove cement laitance, old paint and adhering rubbish and sundries on the surface.
3、彻底清除表面的油污,用克油王清洗剂处理。
3. Thoroughly remove the oil on the surface and treat with King oil cleaning agent.
4、清除积水,并使潮处彻底干燥。
4. Remove the water and dry the damp place thoroughly.
5、表面的清洁需用无尘清扫机及大型吸尘器来完成。
5. The surface cleaning needs dust-free cleaner and large vacuum cleaner.
6、平整的表面允许空隙为2保定平面设计培训 收费岛模具 挡土墙模具 防撞墙模具 防撞墙模具 防撞护栏模具 大棚遮阳网 遮阴网~2.5mm,含水量在6%以下,PH值6~8。
6. The allowable void on the flat surface is 2-2.5mm, the water content is below 6%, and the pH value is 6-8.
7、地坪表面的打毛,需用无尘打磨机来完成,并用吸尘器彻底清洁。
7. The surface of the floor shall be roughened with a dust-free grinder and cleaned thoroughly with a vacuum cleaner.
8、对地坪表面的洞孔和明显凹陷处应用腻子来填补批刮,实干后,打磨吸尘。
8. Putty shall be applied to the holes and obvious depressions on the surface of the floor to fill the batch scraping. After being dry, the dust shall be polished.